Plan to produce: BOMs, MRP, production orders and quality
Define bills of materials and routings, run material requirements planning, convert the results to purchase requisitions or production orders, run the shop floor and inspect quality.
On this page
Process at a glance
- Define BOMs and routingsEngineer / plannerApproved BOM per product; routing with operations per work center.
- Set planning parametersPlannerLead time, safety stock, reorder point and lot sizing per product.
- Run MRPPlannerPurchase, produce and transfer recommendations with peg trace.
- Convert recommendationsPlannerPurchase requisitions or production orders are created.
- Release and scheduleSupervisorWork orders per routing operation placed on work centers and days.
- Execute and inspectOperators / inspectorsQuantities completed, rejects recorded, inspections passed or failed.
- Review costCost accountantMaterial, labor, overhead and subcontracting costs per order.
#Purpose and scope
This chapter follows a manufactured product from its bill of materials to finished goods: master data, material requirements planning (MRP), production orders and work orders, capacity scheduling, quality inspection and costing. The Manufacturing home page lists production orders, work orders, BOMs and overdue jobs.
#Before you start
- Products (finished, semi-finished and raw) exist in the product master, and warehouses are set up (see “Inventory operations”).
- Work centers exist in Work centers; standard steps exist in Operations.
- Sales orders, forecasts and existing production orders are the demand MRP reads, so keep them current.
#1. Bills of materials and routings
- Open BOMs, create the BOM header for the product and add the component lines.
- Build the routing in Routings with its steps in Routing operations; each step names a work center and a sequence.
- Submit the BOM for approval, then approve it.
| Status | Rule |
|---|---|
| Draft | Can be submitted only if it has at least one active line: “Cannot submit a BOM with no active lines.” |
| Pending approval | Waiting for approval. |
| Approved | Approving deactivates the previously active BOM of the same product and type, so only one approved BOM per product/type is active. |
#2. Planning parameters and the master schedule
- In Planning parameters set, per product, the planning group (Raw Material, Finished Goods, Semi-Finished, Packaging), ABC class, preferred vendor, lead time in days, safety stock, reorder point and reorder quantity.
- Choose a lot sizing method: LFL (lot for lot), FOQ (fixed order quantity) or EOQ (economic order quantity), with fixed, minimum and maximum order quantities where relevant.
- Optionally capture demand in Demand forecasts and plan the master production schedule in MPS plans; the MPS workbench shows a product by period matrix with available-to-promise and can recalculate it.
#3. Run MRP
- Open the MRP dashboard.
- Set Plan From and Plan To and tick what to include: Production Orders, Forecasts, Safety Stock.
- Choose the Plan Mode: Regenerative re-plans everything; Net Change re-plans only items whose demand or supply changed since the last run.
- Choose Run MRP. The run header shows the number, status and the totals for purchase, produce and transfer recommendations.
- Review each result: planned quantity, net and gross requirement, stock, safety stock, lot method, required date, suggested order date and what it is pegged to. Use the Peg trace to see the demand behind a line.
- When the run is Completed, choose Confirm to lock it from re-execution.
| Status | Meaning / what you can do |
|---|---|
| Running | Calculation in progress. |
| Completed | Results are ready; Confirm is offered. |
| Draft or Failed | A Re-run action is offered. |
| Confirmed | Locked. Only a Completed run can be confirmed: “Cannot confirm run in … status”. |
#4. Convert recommendations
- Use the All, Purchase, Produce and Transfer tabs (a tab appears only if it has results) and search by product.
- Select the unconverted lines, then convert to Purchase Requisitions (for bought items) or Production Orders (for made items).
- Converted lines are dimmed and marked “Converted to …”; they cannot be converted twice.
#5. Production orders and work orders
A production order is created by conversion, from a sales order, or by hand in Production orders (product, BOM, routing, planned quantity, dates, warehouse, department, project, cost centre, priority Low/Normal/High/Critical). The Materials tab lists required materials and can be populated from the BOM.
| Transition | Rule and effect |
|---|---|
| Draft → Released | Only Draft orders can be released. Opens a WIP entry at standard cost and creates one work order (status Scheduled) per routing operation. |
| Released → In Progress | Only Released orders can start; sets the actual start. |
| In Progress → Completed | Completed quantity must be positive and not exceed the planned quantity. Finished goods are received into the warehouse. |
| Completed → Closed | Only Completed orders can be closed. |
| Draft or Released → Cancelled | Orders already in progress cannot be cancelled. |
#6. Capacity and the shop floor
- In the Capacity schedule drag a work order to another work center or day, or tap it to change the work center and start/end dates. Each cell shows planned versus available hours and the load percentage.
- The Work center board shows live Andon status and Availability, Performance, Quality and OEE for the last 24 hours.
#7. Quality inspection
- Define what is measured in Quality parameters.
- Record an inspection in Quality inspections against a work order or production order: date, inspector, quantity inspected, passed and rejected.
- Enter a measurement per parameter in Inspection results.
| Status | Meaning |
|---|---|
| Pending | Not yet decided |
| Pass | Accepted |
| Fail | Rejected |
| Conditional | Accepted with conditions |
#8. Production costs
Production costs tracks cost lines per production order. Each line has a type — Material, Labor, Overhead or Subcontracting — with quantity, unit cost, total, cost centre and optional work order.
About this guide
- Status
- Partially reviewed
- Application
- BSuit ERP
- Audience
- Production planners, shop-floor supervisors and quality inspectors
- Owner
- BSuit documentation team
- Reviewer
- Not yet reviewed
- Last verified
- Never
- Checked against
- Generated from source revision a36c7a086 on 2026-10-02
- Seen on a running system
- Not yet
- Help version
- 2026.0.0-preview
- Guide ID
erp:article/guide/manufacturing-mrp