Idea to project close: intake, planning, delivery and billing
Take a project idea through intake, create the project from a template, plan the WBS, budget and resources, track risks, issues and change orders, and bill and recognise revenue.
On this page
Process at a glance
- Capture the ideaRequester / PMOIntake moves from idea to review to approved.
- Create the projectPMOProject, WBS, activities and milestones from a template, or converted from an approved intake.
- Plan work and budgetProject managerWork breakdown, activities, budget lines and resource allocation.
- Track the scheduleProject managerGantt, kanban and workload views.
- Manage risks, issues and changesProject managerApproved change orders adjust budget and end date.
- Forecast costProject managerBAC, committed, actual, EAC, ETC and VAC.
- Bill and recognise revenueProject accountantBilling items and percent-complete revenue recognition.
#Purpose and scope
This chapter follows a project from demand intake to billing. The Project Management home page shows budget versus actual, status, completions and overdue attention items, and the Dashboard gives the project view.
#1. Intake: from idea to project
- In Intake create an intake with a code, title, description, business case, requester, estimated cost, estimated benefit and score.
- Move the Stage through Idea, Review, Approved or Rejected.
- Choose Convert on a row that is not rejected or already converted.
#2. Create a project
- Either start from a template: Templates lists reusable blueprints; choose Instantiate and give a project name. BSuit creates the project with its WBS, activities and milestones and reports how many of each.
- Or create it directly in Projects: group, manager, location, status, priority, planned and actual dates, currency, budget, estimated cost and revenue method.
| Field | Values |
|---|---|
| Status | Planned (default), In Progress, On Hold, Completed, Cancelled |
| Priority | Low, Medium (default), High, Critical |
| Revenue method | Unrestricted, Recognition, Contract |
#3. Plan the work, budget and people
- Break the scope down in WBS and Activities; group work under Epics for agile projects.
- Set the working calendar in Calendars and holidays in Calendar exceptions.
- Enter the cost budget by category in Budget lines.
- Allocate people in Resources, with cost and billing rates in Resource rate cards. The Workload heatmap shows allocation by week and flags over-allocation in red.
#4. Track delivery
- Follow the plan on the Gantt and the Kanban board; Sprint analytics shows burndown and velocity for agile projects.
- Log risks in the Risk register and problems in Issues.
| Item | Statuses and values |
|---|---|
| Risk status | Identified (default), Analyzing, Mitigating, Resolved, Accepted, Closed |
| Risk assessment | Probability 1–5 and Impact 1–5, plus owner, trigger, mitigation plan and contingency plan; categories Technical, Financial, Schedule, Resource, External, Quality |
| Issue status | Open (default), In Progress, Resolved, Closed, Deferred |
| Issue severity / type | Low, Medium, High, Critical; Bug, Change Request, Clarification, Blocker, Other |
#5. Change orders
- Record a change request in Change orders with its cost impact and schedule impact in days. Status starts as Draft and can be Submitted.
- Use the Approve or Reject row action to decide it.
#6. Forecast cost and profitability
Cost forecast and P&L shows BAC (budget), Committed, Actual, EAC (forecast), ETC (to complete) and VAC (variance) by cost category, plus margin.
#7. Billing and revenue recognition
- Record billing items in Billing: billing type (Milestone, Time & Material, Fixed Fee, Percent Complete), amount, status Draft, Invoiced or Paid, invoice date and whether it is billable.
- For percent-complete revenue, pick the unbilled receivable and revenue ledgers and choose Recognize.
About this guide
- Status
- Partially reviewed
- Application
- BSuit ERP
- Audience
- Project managers, PMO and project accountants
- Owner
- BSuit documentation team
- Reviewer
- Not yet reviewed
- Last verified
- Never
- Checked against
- Generated from source revision a36c7a086 on 2026-10-02
- Seen on a running system
- Not yet
- Help version
- 2026.0.0-preview
- Guide ID
erp:article/guide/project-delivery
Was this helpful?