HSE: permits to work, incidents and corrective actions to closure
Authorise hazardous work with a permit, record incidents, raise non-conformance reports, complete and verify corrective actions, and close the loop.
On this page
Process at a glance
- Authorise hazardous workRequester, approver, HSE officerA permit goes Draft, Submitted, Approved, Active and Closed.
- Record the incidentReporterThe incident is logged with date, severity and impact.
- Raise an NCRHSE officerA numbered non-conformance report is linked to the incident.
- Work the corrective actionsAction ownerActions move Open, In Progress, Done and Verified.
- Close the NCR and incidentHSE officerClosure is allowed only when nothing is left open.
- MonitorHSE managerOpen incidents, overdue actions, expiring permits and inspections due.
#Purpose and scope
This chapter follows the two HSE chains that BSuit enforces: a permit to work, which must be approved before hazardous work starts, and the incident closure chain (incident, non-conformance report, corrective actions). Risk assessments, risk categories, checklist templates and inspection runs live in the same module and are touched on briefly at the end.
#Before you start
- An approval workflow linked to the PERMIT-WORK record type. Without one, a permit cannot be submitted (“No active workflow is configured for record type ‘PERMIT-WORK’.”).
- Incident categories and severities are set up so incidents can be classified.
- The named HSE permissions are granted to the people who act: hse.permit.activate, hse.permit.close, hse.corrective_action.verify, hse.ncr.raise, hse.ncr.close and hse.incident.close. The seeded HSE Officer role holds all six; superusers pass as well.
#1. Permit to work
- Open Permits to work and add a permit: permit number, type (Hot Work, Confined Space, Working at Height, Electrical, Excavation or General), location, work description, valid from and valid to, hazards and precautions.
- Choose Submit. The permit moves from Draft to Submitted and starts the PERMIT-WORK approval workflow.
- The approver chooses Approve or Reject. Approval sets the status to Approved; rejection sets it to Revoked.
- A supervisor chooses Activate when the work actually starts. The status becomes Active.
- When the work is finished, choose Close. The status becomes Closed.
| Status | Set by | Next step |
|---|---|---|
| Draft | Creation | Submit; dates can still be edited |
| Submitted | Submit | Approver approves or rejects |
| Approved | Workflow approval | Activate |
| Revoked | Workflow rejection | Raise a new permit |
| Active | Activate | Close |
| Closed | Close | None |
| Expired | Background sweep, when an Active permit passes its valid-to | Raise a new permit |
#2. Record an incident
- Open the Incident timeline. It lists every incident, newest first, and can be filtered by severity, status and near misses only. Use its link to the incident list to add a record.
- Enter title, incident date, location, status (Open or Investigating), category, severity, reporter and investigator.
- Tick Near Miss when nothing was injured or damaged. Record injuries, fatalities, property damage, root cause and a photo.
#3. Raise a non-conformance report
- Open the incident and go to the Closure chain tab (save the incident first).
- Choose Raise NCR. BSuit numbers it NCR-yyyy-nnnn, copies the description and root cause from the incident and links it to the incident.
- Severity defaults from the harm recorded: critical if there are fatalities, major if there are injuries, otherwise minor.
#4. Corrective actions
- Add corrective actions against the NCR (title, type, owner, due date).
- Track them on the Corrective actions board: drag a card between columns or use Move to. The columns are Open, In Progress, Done and Verified.
- In the incident’s Closure chain tab you can also choose Mark done on an action.
- When an action is Done, an authorised person chooses Verify. The verifier and time are recorded from the login.
#5. Close the NCR, then the incident
- In the Closure chain tab, choose Close NCR when all its corrective actions are Done or Verified.
- Choose Close incident when no NCR raised from it is still open. The closing user and time are recorded.
- To reopen, choose Reopen on the closed NCR or incident: both return to Investigating.
| You try to | It is refused when |
|---|---|
| Close an NCR | Any corrective action is still open (“Cannot close: n corrective action(s) are still open. Complete and verify them first.”) |
| Close an incident | Any NCR raised from it is still open (“Cannot close: n non-conformance report(s) raised from this incident are still open.”) |
| Verify an action | It is not Done, or is already Verified |
#6. Monitor
HSE dashboard shows open incidents by severity, overdue corrective actions, permits expiring within a window, and inspections due. Each panel links to its list.
#Who can do what
Activating and closing permits, raising and closing NCRs, closing or reopening incidents and verifying corrective actions each need the matching named permission; without it the action fails with “You need the ‘…’ permission to do this.” Approving or rejecting a permit is done by the approver in the workflow. Superusers hold every permission.
About this guide
- Status
- Partially reviewed
- Application
- BSuit ERP
- Audience
- HSE officers, supervisors and site managers
- Owner
- BSuit documentation team
- Reviewer
- Not yet reviewed
- Last verified
- Never
- Checked against